Industrial · Steel PEB · AISC 360 Design project

Steel PEB Building: 40 m wide, tapered portal frames

A 40 × 91 m pre-engineered steel building of about 3,650 m², with 12 bays of tapered portal frames. We designed the members and every connection for wind and seismic loads, then built the complete steel model with each member in its true position and every plate, bolt and base detailed. The finished model now also carries the cladding, gates and reinforced foundations.

Walkthrough of the detailed 3D model: the clad building, the frames under the cladding, an eave knee and the reinforced foundations, with the pedestal ties running down into the footings.
3D model of the PEB building: tapered frames, purlins, girts, bracing and footings
Columns and raftersPlatesPurlins and girtsBracingBoltsFootingsReinforcementCladding

The challenge

The building needed a 40 m wide covered floor, about 91 m long, with a low eave of 5 m. A wide, low building attracts high wind uplift on the roof, and every frame is repeated twelve times, so any extra steel in one frame is multiplied across the whole building.

Our approach

  • Set out a two-span frame (2 × 20 m) with a central column, so the rafters stay shallow and light instead of spanning the full 40 m.
  • Used tapered I-sections for rafters and columns: deep (up to 750 mm) where bending is highest at the eaves and the ridge, shallow where it is not.
  • Applied wind loads to ASCE 7-16 (basic wind speed 47 m/s, exposure C) and seismic loads to ASCE 7-16 by the equivalent lateral force method, then checked 34 strength and 5 serviceability load combinations.
  • Placed roof and wall bracing in the end and middle bays to carry wind along the length of the building into the foundations.
  • Checked all 361 members to AISC 360-16 (LRFD) using the direct analysis method with P-delta. Every member passes; the highest ratio is 0.48 on the rafters and 0.42 on the side columns, so the frame sizes are set by stiffness rather than strength.
  • Designed every connection type for the worst forces across all its locations and all 34 strength load combinations, then modelled each one in place.

From analysis lines to a real steel model

An analysis model puts every member on its centreline, so members overlap at the joints and no plate or bolt can be placed correctly. We rebuilt the structure as a fabrication-ready model:

  • Columns placed with their outer flange on the gridline and the rafters cut back to the column face, so the end plates sit flat on the column flange.
  • Rafters broken into transportable pieces at the section changes (6.67 m and 16.67 m from each eave), joined by bolted end-plate splices.
  • Purlins rotated to the 1:10 roof slope and seated on welded cleats; bracing angles bolted to gusset plates at both ends.
  • Base plates, anchor bolts, shear keys and concrete pedestals at all 51 columns.

The finished model holds 51 columns, 198 rafter pieces and purlins, 60 bracing members, 656 plates and 1,634 bolts.

View inside the building along the frames, showing tapered columns, rafters and purlins
Inside the building: tapered frames at 7.67 m centres with purlins over the rafters.

Cladding, gates and foundations

We then took the model to fabrication level of detail (LOD 400) for the whole building, not only the frames:

  • C-section purlins on bolted cleats with sag rods, and C-section wall girts on welded clips with bolted ends.
  • 0.5 mm galvanised trapezoidal sheeting on the roof and walls, with ridge cap, rake and corner trims and eave gutters.
  • A 5 m roller-shutter gate in each gable, framed with jambs and a header girt, and a personnel door in the side wall.
  • 51 isolated pad footings with pedestals, sized from the support reactions, with the footing mesh and pedestal cages modelled bar by bar.
  • A clash check of the full steel model with no clashes.

Connections

We designed each connection to AISC 360-16 (LRFD) and then checked every one in a component-based finite element model (CBFEM): the plates, welds, bolts and anchors are modelled as they will be built and loaded with the worst forces from all 34 strength load combinations. Bolts and welds are checked to AISC 360-16, plates against a 5% plastic strain limit, and anchor rods, concrete and shear lugs to ACI 318-19.

The finite element checks led to four changes in the steel model:

  • The shear lugs at the side columns now run across the frame, so they bear against the concrete in the direction of the 84 kN frame shear.
  • The splice end plates stand 10 mm proud of the flush flange, so the sloped flange is fully cut and welded to the plate.
  • The purlin cleats on the two gable frames have 4 bolts instead of 2. Two columns of bolts let the joint resist rotation on its own.
  • The pedestal ties continue down through the footing to just above the bottom mesh, holding the starter bars in place.

Connection schedule

ConnectionGoverning forces (LRFD)DetailRatio
Eave kneeM 410 kNmEnd plate 25 mm at the column face, 12 × M24 A325, panel stiffeners0.80
Ridge and column capM 529 kNm, N 276 kNExtended end plates 32 mm, 10 × M30 A325; caps 25 mm, 2 × M24 each side0.68
Rafter splice, 6.07 mM 126 kNmExtended end plates 25 mm, 8 × M24 A3250.36
Rafter splice, 16.07 mM 70 kNmExtended end plates 20 mm, 8 × M24 A3250.24
Side column baseH 84 kN, N 144 kN, uplift 19 kNPlate 20 mm, 4 × 25 mm F1554 Gr 36, shear lug 200 × 150 × 30 across the frame0.75
Central column baseN 284 kN, no upliftPlate 500 × 300 × 20, 4 × 25 mm F1554 Gr 360.10
Gable column baseH 18 kN, uplift 4 kNPlate 300 × 500 × 20, 4 × 19 mm F1554 Gr 36, shear on the rods0.65
Gable column topH 16 kN2 × M20 A3250.15
Purlin to rafter, interior31 kN down, 19 kN up per endCleat 10 mm with stiffener, 2 × M16 A325 each end0.41
Purlin to rafter, gable end30 kN, strut 15 kNCleat 10 mm with stiffener, 4 × M16 A3250.39
Ridge purlinsBolt force 36 kN4 × M20 A325 each end0.41
Roof and wall bracingN 18 kN10 mm gusset, 2 × M20 A3250.10

Analysis

3D analysis model of the steel PEB building with full member sections shown
Analysis model with full member sections: tapered rafters and columns, purlins, and roof and wall bracing.
Elevation of a typical frame: two 20 m spans, 5 m eave, 7 m ridge, pinned bases
Typical frame: two 20 m spans with a central column and pinned bases.
AISC 360-16 member check map, all members below 1.0
Member check results: colour shows the utilisation ratio of each member (1.0 is the code limit).

Results

  • Steel weight of about 142 t, or about 39 kg per m² of floor.
  • All members pass with reserve (rafters 0.48, side columns 0.42, central columns 0.16). Under service loads the rafters deflect about 31 mm (span/640) and the eaves sway less than 2 mm.
  • Every connection passes the finite element check; the highest ratios are 0.80 for the eave knee bolts and 0.75 for the side-column shear lug weld.
  • A complete 3D steel model ready for shop drawings, plus support reactions for the foundation design.
  • The model carries the full envelope and reinforced foundations, with no clashes in the steel.

Deliverables

  • Structural analysis and design report
  • Member schedule with tapered section sizes
  • Connection design calculations and schedule
  • Full 3D model (LOD 400): steel, cladding, gates and doors
  • Foundation sizes and reinforcement
  • Support reactions for the foundation design